chapter 5 生產製造循環 (ii) 淡江大學資訊管理學系 徐煥智整理編撰....
TRANSCRIPT
Chapter 5 生產製造循環 (II)
淡江大學資訊管理學系徐煥智整理編撰
物料需求計劃(Material Requirements Planning)
• 對衍生需求的優先次序規劃
對車子的需求
衍生出
對輪胎的需求
物料需求計劃(Material Requirements Planning)
What to orderHow much to orderWhen to orderWhen to schedule delivery
Note: MRP 用來規劃所有資源的未來需求 .
物料需求計劃(Material Requirements Planning)
MRP
MPS
BOM
InventoryRecords
工令
請購單
物料需求計劃(Material Requirements Planning)
•Bill of Material Structure
1. 彙總式 (Summarized Parts List)
2. 多階式 (Multilevel Bill)
3. 單階式 (Single-Level Bill)
4. 規劃料表 (Planning Bill)
物料需求計劃(Material Requirements Planning)
•彙總式 (Summarized Parts List)
料號 名稱 數量 欄位
B 1
C 1
D 3
E 2
F 1
G 1
項目 A
E(1) F(1)
B(1)
D(1) E(1) G(1)
C(1) D(2)
A
Product Tree
物料需求計劃(Material Requirements Planning)
•多階式 (Multilevel Bill)
F
J K (2)
G(2)
B(2) C
M (2) N
D
X
P
J K (2)
G
L M N(2) O
Y
物料需求計劃(Material Requirements Planning)
•單階式 (Single-Level Bill)
B(2) C D
X
L M N(2) O
Y
F G(2)
B
M (2) N
D
P G
L
J K (2)
G
物料需求計劃(Material Requirements Planning)
•規劃料表 (Planning Bill) - Used to simplify forecasting (MPS, MRP)
Common parts L egs Sides Tops
Table
Leg A40%
Leg B35%
Leg C25%
Side A55%
Side B30%
Side C15%
Top A45%
Top B30%
Top C25%
100%
物料需求計劃(Material Requirements Planning)
用途表 (Where-Used Report)
•與 BOM 相關表格
溯源報表 (Pegging Report)
Where-used reports give the same information as a BOM, butthe where-used report gives the parents for a component whereas the BOM gives the components for a parent.
A pegging report is similar to where-used report. However, the pegging report shows only those parents for which there is an existing requirement.
物料需求計劃(Material Requirements Planning)
•溯源報表 (Pegging Report)
WeekItemNumber
1 2 3 4 5
C 50 125 25 50 150
A 50 25 25 50 50
B 100 100
Pegged Requirements
Source of Requirements
C
C D
B
A
物料需求計劃(Material Requirements Planning)
•MRP Process
Exploding andOffsetting
Gross and NetRequirements
Releasing Orders
物料需求計劃(Material Requirements Planning)
•Exploding and Offsetting - Example
D(L T=1) E(L T=1)
B(L T=2) C(L T=1)
A (L T=1)
WeekPartNumber
1 2 3 4 5
A Planned Order ReceiptPlanned Order Release 50
50
B Planned Order ReceiptPlanned Order Release 50
50
C Planned Order ReceiptPlanned Order Release 50
50
D Planned Order ReceiptPlanned Order Release 50
50
E Planned Order ReceiptPlanned Order Release 50
50
Planned Order
(MPS)
物料需求計劃(Material Requirements Planning)
•Gross and Net Requirement - ExampleWeekPart
Number
1 2 3 4 5
A Gross RequirementProjected Available 20Net RequirementPlanned Order ReceiptPlanned Order Release
20 20 20 20
30
5003030
B Gross RequirementProjected Available 10Net RequirementPlanned Order ReceiptPlanned Order Release
10 10
20
103002020
C Gross RequirementProjected AvailableNet RequirementPlanned Order ReceiptPlanned Order Release
0
30
3003030
D Gross RequirementProjected AvailableNet RequirementPlanned Order ReceiptPlanned Order Release
0
20
2002020
E Gross RequirementProjected AvailableNet RequirementPlanned Order ReceiptPlanned Order Release
0
20
2002020
物料需求計劃(Material Requirements Planning)
•Released Order - Scheduled Receipt
The scheduled receipts row shows the quantities ordered and when theyare expected to be completed and available.
WeekPartNumber
1 2 3 4 5
D Gross RequirementScheduled ReceiptsProjected AvailableNet RequirementPlanned Order ReceiptPlanned Order Release
0
202000
E Gross RequirementScheduled ReceiptsProjected AvailableNet RequirementPlanned Order ReceiptPlanned Order Release
0
202000
Note: Net Requirement = Gross Requirement - Scheduled Receipts - Available Inventory
物料需求計劃(Material Requirements Planning)
MRP 不安定性
• 高階項目的小改變造成低階項目的大改變。• MRP 系統做出的排程若經常改變將傷害 MRP的可信度。
• 變化的原因: MPS 變化、供應商遲交、品質問題、記錄錯誤、意外的異動。
物料需求計劃(Material Requirements Planning)
Fundamental Wrong with MRP
MRP
Flawed Model
)f( numberpart timelead
Note: Lead times are not affected by the status of the plant
MRP II Hierarchy
DemandForecast
AggregatePlanning
ResourcePlanning
MPSRough-Cut
Capacity Planning
MRP
Job Pool
JobRelease
JobDispatching
Capacity RequirementPlanning
BOM
InventoryStatus
RoutingData
Long-RangePlanning
Intermediate-RangePlanning
Short-TermPlanning
CRP
Planned Order Releases
Open Orders
Routing DataCapacity and lead Time
for Process Centers
Shop Calendar
Work Center Load Report
產能需求規劃(Capacity Requirement Planning)
產能需求規劃(Capacity Requirement Planning)
Part Name: Gear Shaft Part Number: SG123Drawing Number: D123X
Operation Work S/U Time Run Time/Piece No. Center (Standard Hours) (Standard Hours) Operation
10 12 1.50 0.2 Turn Shaft 20 14 0.50 0.25 Mill Slot 30 17 0.30 0.05 Drill Hole 40 03 0.45 0.10 Grind 50 Stores Inventory
Routing Data
產能需求規劃(Capacity Requirement Planning)
WorkCenter
QueueTime
WaitTime
MoveTime
AvailableTime
Utilization Efficiency
12 4 1 1 24 100% 100%14 3 1 1 24 100% 100%17 5 1 1 24 100% 100%03 8 1 1 24 100% 100%
Work Center File
產能需求規劃(Capacity Requirement Planning)
Ex: A work center has the following open orders and planned orders for week 20. Calculate the total standard time required (load) on this work center in week 20. Order 222 is already in progress, and there are 100 remaining to run.
OrderQuantity
SetupTime
RunTime
Released Orders
Planned Orders
222333
100150
01.5
0.20.2
444555
200300
32.5
0.250.15
產能需求規劃(Capacity Requirement Planning)
Week 20 21 22 23 24 TotalReleased
Load51.5 45 30 30 25 181.5
PlannedLoad
100.5 120 100 90 100 510.5
Total Load 152 165 130 120 125 692Rated
Capacity140 140 140 140 140 700
Over/UnderCapacity
-12 -25 10 20 15 8
Work Center Load Report
結論