tcm60_ang

Upload: paklan

Post on 05-Jul-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/16/2019 tcm60_ang

    1/8

    TCM 60w w w . m a t i s a . c h

    TRACK CONSTRUCTION MACHINE

  • 8/16/2019 tcm60_ang

    2/8

     TCM 60

    TCM

    TCM

    TCM 60

    Pad insertionTrack laying andpositioning

    Gantry 1Winches forrail pulling

    Sleeper laying andpositioning

    Track Construction Machine TCM 60The TCM 60 is built to lay new track continuously. It uses thesame working principle as the MATISA Track Renewal Trainswhich are internationally renowned for their excellence

    OptionsRail pulling on the platformXPost for rail pad positioning on the sleepersX

     Additional drive wagon (WES)X A second gantryXPositioning and insertion of 10% of the elastic fasteningsX

     Automatic insertion of the “fast clips”X

    TCM 60 MOR (China)

    Basic execution

    Rail pulling tractor 

  • 8/16/2019 tcm60_ang

    3/8

    WES

    TCM 60

    Provisional storage for fasteningsRail insertion

    Gantry 2Fastening insertionRail advancing (2 units)

    Sens de travail

    Rail and sleepers

     transport wagon

    Rail positioning

    Gantry

    Working direction

    Sleeper transport wagon

    Complete execution

    Right of technical modifications reserved

  • 8/16/2019 tcm60_ang

    4/8

    1 12 23 34 45 56 6

    Working direction

    Working direction1,8 km = 12 rails of 300 meters

    Worksite set-upThe initial machine set-up at a new worksite is an autonomousand very rapid process, as all the units required are carried bythe machine itself.

     After the initial set-up, continuation of work at the worksiteonly requires the exchange of the sleeper or rail and sleepertransport wagons; thus there is no interruption to the tracklaying process.

    Rail and sleeper transportationThe adjacent drawing shows the procedure when the choice ismade to pull the rails from the machine onto the platform. Thissolutions avoids trains crossing on the work-site.

  • 8/16/2019 tcm60_ang

    5/8

    Working direction

    Working direction

    2 winches at the front of the TCM to pull the rail to theX

    system2 pairs of driven rollers under the WES, to push the railsX

    To guide the rails and to avoid any damage to the platform, supportrollers are placed manually every 10 meters directly onto theplatform.

    These rollers are picked up when the sleepers are laid.

    Rail pulling on the platformThis operation, which is not simultaneous with the sleeper

    laying, requires the following equipment:

    1 caterpillar tractor XGuiding rollers to be installed along the machine and theXsupplementary wagonRollers to be placed every 10 meters along the platformX

    Rail passage holders

    Rail guidinghead

    Platformroller 

    This operation is not simultaneous with the sleeperlaying

    Rail and sleepertransport wagon

  • 8/16/2019 tcm60_ang

    6/8

    5

    1

    3

    2

    4

    6

    7

     TCM 60

    Working direction

    Working direction

    Track laying unitThe technique used for laying the sleepers is the same as thatdeveloped and used on the latest generation of track renewaltrains. Thanks to its rapid, short movements, this laying unit isrenown as the most reliable and accurate currently available onthe market.

    Drawings 1 to 5 on the left show the sleeper’s cinematic in thelaying unit.

    Drawings 6 and 7 show that before adjusting the distancebetween the sleepers, they are laid on the track formationensuring constant and regular spacing.

    P2: post for rail positioning

    P1: post for sleepersand machine guiding

    Cabin work postsThe cabin of the TCM 60 features two work posts:

    one for laying the sleepers and guiding the machineXone for laying the rails on the sleepersX

  • 8/16/2019 tcm60_ang

    7/8

    Guiding the machine A line painted on the track platform helps the operator toguide the caterpillar; moreover the working unit can be movedlaterally to refine the guiding precision.

    Equipment for connection to the

    existing rail

     Alignment tolerance to the crawler ± 50 mmX

     Alignment tolerance to the working group lateral movementX± 20 mm

    Guideline spray-painted on the platformCrawlers, controlled bythe sleepers operator 

    Laying group, with lateral displacement controlWorking post

    Right of technical modifications reserved

  • 8/16/2019 tcm60_ang

    8/8

    v14.00 - 0209

    MATISA S.A.S.

    9, rue de l’Industrie

    Z. I. Les Sablons

    FR-89100 Sens

    Tél.: +33-386 95 83 35

    Fax: +33-386 95 36 94

    E-mail: [email protected] 

    MATISA Japan Co., Ltd.

    JR Hatchobori Bldg., 8F3-25-10 Hatchobori, Chuo-ku

    JP-Tokyo 104-0032

    Tel.: +81-3-5540-8211

    Fax: +81-3-5540-8220

    E-mail: [email protected]

    MATISA Matériel Industriel S.A.

     Arc-en-Ciel 2

    Case postale

    CH-1023 Crissier 1

    Tél.: +41-21-631 21 11

    Fax: +41-21-631 21 68

    E-mail: [email protected]

    MATISA Maschinen GmbH

    Kronenstrasse 2DE-78166 Donaueschingen

    Tel.: +49-771 15 80 63

    Fax: +49-771 15 80 64

    E-mail: [email protected]

    MATISA S.p.A.

     Via Ardeatina Km 21

    IT-00040 Pomezia/

    Santa Palomba (RM)

    Tel.: +39-06-918 291

    Fax: +39-06-919 84 574

    E-mail: [email protected]

    MATISA (U.K.) Ltd

    P.O. Box 202GB-Scunthorpe DN 15 6XR

    Tel.: +44-17-248 770 00

    Fax: +44-17-248 770 01

    E-mail: [email protected]

    MATISA Matériel Industriel S.A.

    Sucursal Española

    C/Francia 39

    Poligono Industrial “La Estacion”

    ES-28971 Griñon (Madrid)

    Tel.: +34-91-814 01 71

    Fax: +34-91-814 11 94

    E-mail: [email protected]

    Technical specifcationsOverall Length (without WES)X .........................26’650 mmMaximum width (without gantry rail)X  .................2’900 mmHeight with gantry craneX ..................................4’200 mmWeight without gantryX ................................................70 tEngine power X .....................................................285 kWWorking speed up toX ...................16 sleepers per minuteMax. speed in convoyX  .......................................100 km/hPivots center spacingX .....................................19’300 mmWheel diameter X .................................................920 mmMinimum working radiusX .......................................250 mMinimum travelling radiusX  .....................................150 m

     Vehicle gaugeX ...........................................................UICMaximum sleeper lengthX ..................................2’600 mmLifting capacity of the craneX  .................................22,5 tm