111910_mec_8910a_lecture_6

Upload: miguel-henao

Post on 08-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    1/59

    MEC8910 2010-11

    MEC 8910A

    WORKFLOWHOW TO SUCCESSFULLYCOMPLETE A PROJECT IN

    AERONAUTICAL INDUSTRY

    Lecture 6

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    2/59

    MEC8910 2010-11 2

    LECTURE 5 RECAP PRE-DESIGN ENGINEERING PACKAGES & DRAWINGS

    APPROVAL CYCLE PROCUREMENT

    DESIGN REVIEWS

    DEVELOPMENT REMOVAL

    MANAGING CHANGES

    TYPE BOARD REVIEWS (initial, interim & final)

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    3/59

    MEC8910 2010-11 3

    SOURCE SELECTION &

    QUALIFICATION

    Outsourcing

    decision

    ENGINEERING

    Procurement Specification (PS),

    Source Control Drawing (SCD) or

    Technical Requirements

    Document (TRD) release & vendor

    SOW update with required

    CDRLs listing & due dates

    PROCUREMENTsend RFQ to vendors

    with due date & submit

    quotes to engineering

    for technical review

    Preliminary Source

    Selection meeting

    Engineering

    Detailed technical data

    review & evaluation

    Engineering &

    Procurement

    Technical Negotiations

    Procurement

    & Vendors

    Memorandum of

    Agreement

    Final Evaluation

    meeting

    Source

    selection

    CDRLs

    Delivery,

    data review &

    certification testing

    Vendorapproval

    Qualified Parts &

    Vendors List database

    update

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    4/59

    MEC8910 2010-11 4

    LECTURE 5 RECAP PRE-DESIGN

    ENGINEERING PACKAGES & DRAWINGS

    APPROVAL CYCLE

    PROCUREMENT

    DESIGN REVIEWS

    DEVELOPMENT REMOVAL

    MANAGING CHANGES

    TYPE BOARD REVIEWS (initial, interim & final)

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    5/59

    MEC8910 2010-11 5

    DESIGN REVIEWS Design reviews are an essential quality

    assurance tool in achieving a project withincost & schedule.

    It has many objectives such as:

    Validation of the design requirements against thecertification basis and the customer requirements

    Early detection of required design changes

    Early detection of risk areas

    Enable junior engineers to benefit from experienceof the senior engineers

    Third party review of the work done

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    6/59

    MEC8910 2010-11 6

    DESIGN REVIEWS Typical Commercial Design Reviews

    Statement of Work Review (SOWR)

    Preliminary Design Review (PDR)

    Critical Design Review (CDR)

    Other Military Type Design Reviews SRR System Requirements Review

    SDR System Design Review

    SSR Software Specification Review

    TRR Test Readiness Review FRQ Formal Qualification Review (same as

    Commercial Type Board Meeting)

    PRR Production Readiness Review

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    7/59

    MEC8910 2010-11 7

    Define Requirements & Risks

    Develop Concept & Risk Mitigation

    Pre-design Definition

    Design & Develop

    Prototyping

    Product Validation

    Gate 1

    Gate 2

    Gate 3

    Gate 4

    Gate 5

    SOWRSOWR

    SRRSRR

    PDRPDR CDRCDR

    TRRTRR FQRFQR

    PRRPRR

    SDRSDR

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    8/59

    MEC8910 2010-11 8

    DESIGN PHASE PRE-DESIGN

    ENGINEERING PACKAGES & DRAWINGS

    APPROVAL CYCLE

    PROCUREMENT

    DESIGN REVIEWS

    DEVELOPMENT REMOVAL

    MANAGING CHANGES

    TYPE BOARD REVIEWS (initial, interim & final)

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    9/59

    MEC8910 2010-119

    DEVELOPMENT REMOVAL While EMU use significantly reduces aircraft

    reworks, often first installation will revealdesign change requirements such as design

    oversights or tolerance stack up problems. This first installation is typically referred to as

    the development removal, were engineering,

    manufacturing, planning & quality assurancedepartments through associated effortsresolve all installation & functionality issues.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    10/59

    MEC8910 2010-1110

    DESIGN PHASE PRE-DESIGN

    ENGINEERING PACKAGES & DRAWINGS

    APPROVAL CYCLE

    PROCUREMENT

    DESIGN REVIEWS

    DEVELOPMENT REMOVAL

    MANAGING CHANGES

    TYPE BOARD REVIEWS (initial, interim & final)

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    11/59

    MEC8910 2010-1111

    MANAGING CHANGES

    Your ultimate goal is to minimize changes,do the right thing the first time.Unfortunately, the larger the project is thechanges are more or less inevitable.

    There are basically two types of changes:

    Scope changesDesign changes

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    12/59

    MEC8910 2010-1112

    SCOPE & DESIGN CHANGES Scopes changes

    These are new requirements; additional budgetrequired over the initial authorized budget.

    Examples for Bell 429EP could be because customer asks

    for Emergency flotation system.

    Inlet barrier filter

    Category A Performance

    Design changes

    Modifications to make it work and/or to make itcertifiable; must be absorbed within the authorizedbudget.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    13/59

    MEC8910 2010-1113

    SCOPE CHANGES(Potential Examples from Bell

    429EP)

    Emergency

    Flotation

    System

    Category A

    Performance

    Inlet Barrier

    Filter

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    14/59

    MEC8910 2010-1114

    SCOPE CHANGES

    Define the new requirements and identifyupdates required to the SOW.

    Assess impact on the baseline SOW &certification basis and estimate time & costimplications of the new requirements.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    15/59

    MEC8910 2010-1115

    SCOPE CHANGES

    Submit to management for additional budget& schedule change approval

    Do not start the work until it is approved

    Delays in getting additional approval mayhave impact on cost & schedule; submit atime phase approval schedule. If approvedwithin two weeks - $45,000 & 2 weeksdelay, if approved within one month -$180,000 & 5 weeks delay.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    16/59

    MEC8910 2010-1116

    DESIGN CHANGES Often needed to deliver an acceptable &

    functional product. Once again, they arealmost inevitable.

    Due most to unanticipated or changedconditions:

    More specific knowledge

    Actual conditions

    Rework

    New Technology

    Regulatory Agency regulations interpretation

    Change of personnel

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    17/59

    MEC8910 2010-11 17

    DESIGN CHANGES

    Eats up contingency funds & projectschedule buffers very fast, be careful!!!

    Early detection of required design changeswill minimize cost & schedule implications.

    Proper planning, right cert. basis

    identification, good communication, propertechnical supervision (design reviews) areall conducive to doing it right the first time.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    18/59

    MEC8910 2010-11 18

    DESIGN PHASE PRE-DESIGN

    ENGINEERING PACKAGES & DRAWINGS

    APPROVAL CYCLE

    PROCUREMENT

    DESIGN REVIEWS

    DEVELOPMENT REMOVAL

    MANAGING CHANGES

    TYPE BOARD REVIEWS (initial, interim & final)

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    19/59

    MEC8910 2010-11 19

    TYPE BOARD REVIEWS Type Board meetings (Initial, Interim & Final)

    also part of the design validation processagainst the approved certification basis.

    These meetings are held with the following

    respective objectives: To present the intended aircraft configuration and

    Certification Plan & Certification Basis approval.

    To present project status and resolve outstanding

    certification issues (i.e. Issue Papers). To finalize certification issues and obtain TC or

    STC approval.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    20/59

    MEC8910 2010-11 20

    PROJECT EXECUTION ENGINEERING EFFORT

    DESIGN PHASE

    PROTOTYPES & DEVELOPMENT FLIGHT

    TESTING

    CERTIFICATION TESTING

    COST & SCHEDULE TRACKING

    TRANSPORT CANADA APPROVAL

    TYPE BOARD REVIEWS

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    21/59

    MEC8910 2010-11 21

    NP&SI PROCESS SUMMARY

    PHASE 1: Define Requirements & Risks

    PHASE 2: Develop Concept & Risk Mitigation

    PHASE 3: Pre-design Definition

    PHASE 4: Design & Develop

    PHASE 5: Prototyping

    PHASE 6: Product Validation

    PHASE 7: Transition to Manuf/Service

    Gate 1

    Strategic

    Plan Input

    Deliverables Defined

    and completed beforeleaving each Gate

    Gate 2

    Gate 3

    Gate 4

    Gate 5

    Gate 6

    Gate 7

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    22/59

    MEC8910 2010-11 22

    PROTOTYPES Prototype aircraft are used throughout the

    development testing & certification testing phase.Can be manufactured faster and will never have a

    C of A.

    These aircraft are typically not entirely productionaircraft representative. consequently, they can onlybe used for certification testing where a similarityargument can be accepted by the regulatory agency.

    Requires Aircraft Limitations Report & experimental flight

    test permit approval

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    23/59

    MEC8910 2010-11 23

    DEVELOPMENT TESTING

    This testing phase is to explore the targetflight envelope, identify problem areas &safety margins. It can also include

    certification testing dry runs.

    Problem areas are assessed and resolvedthough aircraft configuration changes,

    engine and/or transmission performanceincrease or aircraft limitations acceptance.

    May require re-testing

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    24/59

    MEC8910 2010-11 24

    DEVELOPMENT TESTING

    New Rotor

    Ground resonance / Aeromechnical /Torsional Stability

    Loads Performance

    Handling Qualities (HQs)

    Engine / drive system vibrations

    Ride quality (FRAHMS)

    AFCS

    Initial cut at gains / scheduling

    Autopilot Development

    Flight Director Development

    Prototype to Support Development Testing:

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    25/59

    MEC8910 2010-11 25

    PROJECT EXECUTION ENGINEERING EFFORT

    DESIGN PHASE

    PROTOTYPES & DEVELOPMENTFLIGHT TESTING

    CERTIFICATION TESTING

    COST & SCHEDULE TRACKING

    TRANSPORT CANADA APPROVAL

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    26/59

    MEC8910 2010-11 26

    CERTIFICATION TESTING

    Certification testing, delegated or not, isconducted to show satisfactorycompliance to regulations within definedparameters.

    Aircraft configuration conformity inspection

    per to test plan requirements is to becompleted prior to test start.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    27/59

    MEC8910 2010-11 27

    CERTIFICATION TESTING When the test is not delegated, the

    regulatory agency will often conduct testplan matrix spot check or perform specifictest areas then delegate the remaining ofthe tests to the DAO.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    28/59

    MEC8910 2010-11 28

    CERTIFICATION TESTING

    For both development & certificationtesting, some tests are dependent on

    specific temperature, density altitudeand/or wind conditions. It may generateoff-site testing requirements and/or delayswaiting for the right conditions.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    29/59

    MEC8910 2010-11 29

    CERTIFICATION TESTING(Example Flight Tests for the New 429EP)

    Load Level Survey

    Hot Weather

    Engine Vibration

    Drive Shaft Vibration

    Torsional Vibration Engine Cooling

    Tailboom Temperature Survey

    Hot Fuel

    Oil System Test

    Inlet Distortion Inlet Icing

    Handling Qualities

    Performance

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    30/59

    MEC8910 2010-11 30

    CERTIFICATION TESTING(Example Flight Tests for the New 429EP)

    Tail Rotor Flapping

    Cat A Runway

    Cat A Ground Helipad

    Noise Survey

    Autopilot Certification

    Controls Proof Load

    Indirect Lightning

    Cold Soak

    Cockpit Cooling

    Cockpit Lighting EMI / EMC

    Avionics System

    Function & Reliability (F&R)

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    31/59

    MEC8910 2010-11 31

    PROJECT EXECUTION ENGINEERING EFFORT

    DESIGN PHASE

    PROTOTYPES & DEVELOPMENTFLIGHT TESTING

    CERTIFICATION TESTING

    COST & SCHEDULE TRACKING

    TRANSPORT CANADA APPROVAL

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    32/59

    MEC8910 2010-11 32

    COST & SCHEDULE TRACKING

    Rigorous cost & schedule trackingthroughout its duration is most important in

    any projects, it may seriously affect designchanges decisions.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    33/59

    MEC8910 2010-11 33

    COST & SCHEDULE TRACKING Cost tracking by WBSE is done by comparing

    the following values: Planned to date: $ 45,000

    Actual to date: $ 55, 000

    Budget: $ 165,000 Estimated at completion $ 185,000

    Variance (-$20,000)

    Your contingency is busted and some other WBSE

    contingency budgets will need to absorb it. If higheractuals were due to a scope change, the budgetwould require an increase with zero value variance.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    34/59

    MEC8910 2010-11 34

    COST & SCHEDULE TRACKING

    Schedule tracking is done using a baselineGantt chart with regular updates to reflectactuals.

    A (6 days)A (9 days)

    BaselineActuals, late finish,

    schedule delays & nocost impact

    (3 days added)

    Late start

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    35/59

    MEC8910 2010-11 35

    PROJECT EXECUTION

    ENGINEERING EFFORT

    DESIGN PHASE

    PROTOTYPES & DEVELOPMENTFLIGHT TESTING

    CERTIFICATION TESTING

    COST & SCHEDULE TRACKING

    TRANSPORT CANADA APPROVAL

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    36/59

    MEC8910 2010-11 36

    TCAC INVOLVEMENT Regulatory Agencies involvement, not limited

    but coordinated through TCAC, throughoutthe planning & the execution phase of theprogram is essential to avoid missing out

    certification requirements.

    It may cause delays but it certainly reducesrisks and reworks.

    Communication with regulatory agency is tobe done through the OEM/DAO Airworthinessdepartment or through the company CDs.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    37/59

    MEC8910 2010-11 37

    TCAC INVOLVEMENT For example, a Canadian OEM has just

    obtained its TC with TCAC on a new aircraftmodel. One of its first customers is US

    operator which must operate its aircraft underUS registry. During the FAA TC validationprocess, FAA decides to impose specialconditions on a particular aircraft system that

    necessitate major design change. OEM inturn may lose this sale and potentially a widemarket share until it incorporates the change.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    38/59

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    39/59

    MEC8910 2010-11 39

    TCAC INVOLVEMENT

    CDs should maintain weekly, if not daily,contacts with their TCAC counterpart tokeep them abreast of project development

    and/or to obtain a concession/concurrenceon technical issue.

    Any CD & TCAC specialist verbalagreement is to be documented (contact

    report), submitted to TCAC specialist forvalidation and distributed to all involved.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    40/59

    MEC8910 2010-11 40

    NP&SI PROCESS SUMMARY

    PHASE 1: Define Requirements & Risks

    PHASE 2: Develop Concept & Risk Mitigation

    PHASE 3: Pre-design Definition

    PHASE 4: Design & Develop

    PHASE 5: Prototyping

    PHASE 6: Product Validation

    PHASE 7: Transition to Manuf/Service

    Gate 1

    Strategic

    Plan Input

    Deliverables Defined

    and completed beforeleaving each Gate

    Gate 2

    Gate 3

    Gate 4

    Gate 5

    Gate 6

    Gate 7

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    41/59

    MEC8910 2010-11 41

    PRODUCTION Factors affecting the certificated aircraft

    configuration and documentation onceproduction commences can include

    Modifications to the design due to The prototype aircraft were not 100%

    representative of final production standard

    Production easement Quicker, cheaper, fewer

    parts Component reliability less than expected

    New requirements: customer, foreign certification

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    42/59

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    43/59

    MEC8910 2010-11 43

    POST-CERTIFICATION Factors affecting the certificated aircraft

    configuration and documentation post-certification include

    Modifications to the design due to

    In-service failures

    Environmental factors

    Aging aircraft

    Changes to the operating and crew procedures

    Maintenance tasks and their periodicity Allowable deficiencies (MMEL Master Minimum

    Equipment List)

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    44/59

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    45/59

    MEC8910 2010-11 45

    CHANGED PRODUCT RULE

    Why was Changed Product Rule introduced? To make major design changes and derivatives of older

    aircraft e.g. Boeing 737 comply with the same airworthinessstandards as new designs of aircraft e.g. Airbus A320.

    What happened before CPR?

    Before CPRWhen a design change to an existingaeronautical product was introduced the amendment level ofthe regulations was the same as the original TC.

    So the Boeing 737 derivatives (737-200, -300, -400, -500,-600, -600NG, -700, -800 and 900 were all certificated tothe same amendments as applied to the original 737 aircraft,

    decades before !! The new Airbus A320, a similar aircraft to the 737, had to be

    certificated to the latest amendments of the regulations.

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    46/59

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    47/59

    MEC8910 2010-11 47

    CHANGED PRODUCT RULE

    Substantial Change

    Section 511.14 and 513.14 of the CARs

    require that an applicant obtain a new type

    certificate if the scope and nature of theproposed change in design, configuration,

    power, power limitations (engine), or

    weight are so extensive that a substantially

    complete investigation of compliance withthe applicable standards is required.

    (Source: AC 500-016)

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    48/59

    MEC8910 2010-11 48

    CHANGED PRODUCT RULE

    Substantial Change

    The OEM must apply for a new TypeCertificate if the change in design, power,

    thrust or weight is extensive. For example: Change from a high wing to a low wing, or vice-versa

    Change of empennage configuration (from cruciform toT-tail)

    Overall power/thrust increase of more than 50%

    Change in flight control concept, i.e. change to fly-by-wire

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    49/59

    MEC8910 2010-11 49

    CHANGED PRODUCT RULE

    Significant ChangeAdditionally, subsection 511.13(3) and 513.07(3) of the CARs

    define a significant change based on whether or not one or

    more of the three criteria applies:

    (a) the general configuration is not retained;(b) the principles of construction are not retained; and

    (c) the assumptions used for certification of the product do

    not remain valid. In many cases, a significant change will

    involve more than one of these criteria and will, by its

    very nature, be obvious and distinct from other productimprovements or production changes.

    (Source: AC 500-016)

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    50/59

    MEC8910 2010-11 50

    CHANGED PRODUCT RULE

    Significant Change

    The OEM must use the latest amendmentlevel (unless its impractical and/or no

    impact on safety !!) if the change issignificant. For example: Change in fuselage length or diameter

    Change in wing sweep angle of

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    51/59

    MEC8910 2010-11 51

    CHANGED PRODUCT RULE

    How do we decide if we have aSubstantial or Significant change?

    Transport Canada has published an

    Airworthiness Manual Advisory AC 500-016 to help us decide

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    52/59

    MEC8910 2010-11 52

    FINAL EXAMINATIONWhat we have covered ...What we have covered ...

    Types of requirement

    Abbreviation & definition

    NP&SI Process Risk & Contingency

    Functional Hazard Analysis Criticalities

    System Safety Analysis Fault Tree Analysis

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    53/59

    MEC8910 2010-11 53

    TYPES OF REQUIREMENT: ABBREVIATIONS & DEFINITION

    TYPE DESIGN & TYPE CERTIFICATE

    SUPPLEMENTAL TYPE CERTIFICATE (STC)

    FAR, CAR, EASA, JAR, OEM, AC

    IPT, NP&SI PROCESS

    SPECIAL CONDITION

    NPRM

    EXEMPTION

    EQUIVALENT LEVEL OF SAFETY

    TSO

    ICAO DAO, CD (DER)

    CERTIFICATION BASIS & GENERAL COMPLIANCE PLAN (GCP)

    DOC, NPV, ROIC, IRR

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    54/59

    MEC8910 2010-11 54

    NP&SI PROCESS SUMMARY

    PHASE 1: Define Requirements & Risks

    PHASE 2: Develop Concept & Risk Mitigation

    PHASE 3: Pre-design Definition

    PHASE 4: Design & Develop

    PHASE 5: Prototyping

    PHASE 6: Product Validation

    PHASE 7: Transition to Manuf/Service

    Gate 1

    Strategic

    Plan Input

    Deliverables Defined

    and completed beforeleaving each Gate

    Gate 2

    Gate 3

    Gate 4

    Gate 5

    Gate 6

    Gate 7

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    55/59

    MEC8910 2010-11 55

    CERTIFICATION

    Originalapproval ofan aircraft

    design

    Approval of amanufacturers QCsystem to produce

    aircraft that replicate theapproved design

    Approval of an individualaircraft that conforms to the

    type design and is in acondition for safe operation

    Monitoring safetyperformance of

    approved product,production QCsystem & taking

    corrective action toensure continued

    integrity

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    56/59

    MEC8910 2010-11 56

    Functional Hazard Assessment

    Source: SAE ARP 4761

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    57/59

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    58/59

    MEC8910 2010-11 58

    FINAL EXAMINATION

    What we have covered What we have covered

    Development Removal

    Managing Changes

    Prototype & Development Testing

    Transport Canada Approval

    Production

    Post-Certification (Changed Product Rule)

  • 8/7/2019 111910_MEC_8910A_LECTURE_6

    59/59

    MEC8910 2010-11 59

    CLOSING REMARKS

    Anyquestions?Anyquestions?