111910_mec_8910a_lecture_6
TRANSCRIPT
-
8/7/2019 111910_MEC_8910A_LECTURE_6
1/59
MEC8910 2010-11
MEC 8910A
WORKFLOWHOW TO SUCCESSFULLYCOMPLETE A PROJECT IN
AERONAUTICAL INDUSTRY
Lecture 6
-
8/7/2019 111910_MEC_8910A_LECTURE_6
2/59
MEC8910 2010-11 2
LECTURE 5 RECAP PRE-DESIGN ENGINEERING PACKAGES & DRAWINGS
APPROVAL CYCLE PROCUREMENT
DESIGN REVIEWS
DEVELOPMENT REMOVAL
MANAGING CHANGES
TYPE BOARD REVIEWS (initial, interim & final)
-
8/7/2019 111910_MEC_8910A_LECTURE_6
3/59
MEC8910 2010-11 3
SOURCE SELECTION &
QUALIFICATION
Outsourcing
decision
ENGINEERING
Procurement Specification (PS),
Source Control Drawing (SCD) or
Technical Requirements
Document (TRD) release & vendor
SOW update with required
CDRLs listing & due dates
PROCUREMENTsend RFQ to vendors
with due date & submit
quotes to engineering
for technical review
Preliminary Source
Selection meeting
Engineering
Detailed technical data
review & evaluation
Engineering &
Procurement
Technical Negotiations
Procurement
& Vendors
Memorandum of
Agreement
Final Evaluation
meeting
Source
selection
CDRLs
Delivery,
data review &
certification testing
Vendorapproval
Qualified Parts &
Vendors List database
update
-
8/7/2019 111910_MEC_8910A_LECTURE_6
4/59
MEC8910 2010-11 4
LECTURE 5 RECAP PRE-DESIGN
ENGINEERING PACKAGES & DRAWINGS
APPROVAL CYCLE
PROCUREMENT
DESIGN REVIEWS
DEVELOPMENT REMOVAL
MANAGING CHANGES
TYPE BOARD REVIEWS (initial, interim & final)
-
8/7/2019 111910_MEC_8910A_LECTURE_6
5/59
MEC8910 2010-11 5
DESIGN REVIEWS Design reviews are an essential quality
assurance tool in achieving a project withincost & schedule.
It has many objectives such as:
Validation of the design requirements against thecertification basis and the customer requirements
Early detection of required design changes
Early detection of risk areas
Enable junior engineers to benefit from experienceof the senior engineers
Third party review of the work done
-
8/7/2019 111910_MEC_8910A_LECTURE_6
6/59
MEC8910 2010-11 6
DESIGN REVIEWS Typical Commercial Design Reviews
Statement of Work Review (SOWR)
Preliminary Design Review (PDR)
Critical Design Review (CDR)
Other Military Type Design Reviews SRR System Requirements Review
SDR System Design Review
SSR Software Specification Review
TRR Test Readiness Review FRQ Formal Qualification Review (same as
Commercial Type Board Meeting)
PRR Production Readiness Review
-
8/7/2019 111910_MEC_8910A_LECTURE_6
7/59
MEC8910 2010-11 7
Define Requirements & Risks
Develop Concept & Risk Mitigation
Pre-design Definition
Design & Develop
Prototyping
Product Validation
Gate 1
Gate 2
Gate 3
Gate 4
Gate 5
SOWRSOWR
SRRSRR
PDRPDR CDRCDR
TRRTRR FQRFQR
PRRPRR
SDRSDR
-
8/7/2019 111910_MEC_8910A_LECTURE_6
8/59
MEC8910 2010-11 8
DESIGN PHASE PRE-DESIGN
ENGINEERING PACKAGES & DRAWINGS
APPROVAL CYCLE
PROCUREMENT
DESIGN REVIEWS
DEVELOPMENT REMOVAL
MANAGING CHANGES
TYPE BOARD REVIEWS (initial, interim & final)
-
8/7/2019 111910_MEC_8910A_LECTURE_6
9/59
MEC8910 2010-119
DEVELOPMENT REMOVAL While EMU use significantly reduces aircraft
reworks, often first installation will revealdesign change requirements such as design
oversights or tolerance stack up problems. This first installation is typically referred to as
the development removal, were engineering,
manufacturing, planning & quality assurancedepartments through associated effortsresolve all installation & functionality issues.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
10/59
MEC8910 2010-1110
DESIGN PHASE PRE-DESIGN
ENGINEERING PACKAGES & DRAWINGS
APPROVAL CYCLE
PROCUREMENT
DESIGN REVIEWS
DEVELOPMENT REMOVAL
MANAGING CHANGES
TYPE BOARD REVIEWS (initial, interim & final)
-
8/7/2019 111910_MEC_8910A_LECTURE_6
11/59
MEC8910 2010-1111
MANAGING CHANGES
Your ultimate goal is to minimize changes,do the right thing the first time.Unfortunately, the larger the project is thechanges are more or less inevitable.
There are basically two types of changes:
Scope changesDesign changes
-
8/7/2019 111910_MEC_8910A_LECTURE_6
12/59
MEC8910 2010-1112
SCOPE & DESIGN CHANGES Scopes changes
These are new requirements; additional budgetrequired over the initial authorized budget.
Examples for Bell 429EP could be because customer asks
for Emergency flotation system.
Inlet barrier filter
Category A Performance
Design changes
Modifications to make it work and/or to make itcertifiable; must be absorbed within the authorizedbudget.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
13/59
MEC8910 2010-1113
SCOPE CHANGES(Potential Examples from Bell
429EP)
Emergency
Flotation
System
Category A
Performance
Inlet Barrier
Filter
-
8/7/2019 111910_MEC_8910A_LECTURE_6
14/59
MEC8910 2010-1114
SCOPE CHANGES
Define the new requirements and identifyupdates required to the SOW.
Assess impact on the baseline SOW &certification basis and estimate time & costimplications of the new requirements.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
15/59
MEC8910 2010-1115
SCOPE CHANGES
Submit to management for additional budget& schedule change approval
Do not start the work until it is approved
Delays in getting additional approval mayhave impact on cost & schedule; submit atime phase approval schedule. If approvedwithin two weeks - $45,000 & 2 weeksdelay, if approved within one month -$180,000 & 5 weeks delay.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
16/59
MEC8910 2010-1116
DESIGN CHANGES Often needed to deliver an acceptable &
functional product. Once again, they arealmost inevitable.
Due most to unanticipated or changedconditions:
More specific knowledge
Actual conditions
Rework
New Technology
Regulatory Agency regulations interpretation
Change of personnel
-
8/7/2019 111910_MEC_8910A_LECTURE_6
17/59
MEC8910 2010-11 17
DESIGN CHANGES
Eats up contingency funds & projectschedule buffers very fast, be careful!!!
Early detection of required design changeswill minimize cost & schedule implications.
Proper planning, right cert. basis
identification, good communication, propertechnical supervision (design reviews) areall conducive to doing it right the first time.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
18/59
MEC8910 2010-11 18
DESIGN PHASE PRE-DESIGN
ENGINEERING PACKAGES & DRAWINGS
APPROVAL CYCLE
PROCUREMENT
DESIGN REVIEWS
DEVELOPMENT REMOVAL
MANAGING CHANGES
TYPE BOARD REVIEWS (initial, interim & final)
-
8/7/2019 111910_MEC_8910A_LECTURE_6
19/59
MEC8910 2010-11 19
TYPE BOARD REVIEWS Type Board meetings (Initial, Interim & Final)
also part of the design validation processagainst the approved certification basis.
These meetings are held with the following
respective objectives: To present the intended aircraft configuration and
Certification Plan & Certification Basis approval.
To present project status and resolve outstanding
certification issues (i.e. Issue Papers). To finalize certification issues and obtain TC or
STC approval.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
20/59
MEC8910 2010-11 20
PROJECT EXECUTION ENGINEERING EFFORT
DESIGN PHASE
PROTOTYPES & DEVELOPMENT FLIGHT
TESTING
CERTIFICATION TESTING
COST & SCHEDULE TRACKING
TRANSPORT CANADA APPROVAL
TYPE BOARD REVIEWS
-
8/7/2019 111910_MEC_8910A_LECTURE_6
21/59
MEC8910 2010-11 21
NP&SI PROCESS SUMMARY
PHASE 1: Define Requirements & Risks
PHASE 2: Develop Concept & Risk Mitigation
PHASE 3: Pre-design Definition
PHASE 4: Design & Develop
PHASE 5: Prototyping
PHASE 6: Product Validation
PHASE 7: Transition to Manuf/Service
Gate 1
Strategic
Plan Input
Deliverables Defined
and completed beforeleaving each Gate
Gate 2
Gate 3
Gate 4
Gate 5
Gate 6
Gate 7
-
8/7/2019 111910_MEC_8910A_LECTURE_6
22/59
MEC8910 2010-11 22
PROTOTYPES Prototype aircraft are used throughout the
development testing & certification testing phase.Can be manufactured faster and will never have a
C of A.
These aircraft are typically not entirely productionaircraft representative. consequently, they can onlybe used for certification testing where a similarityargument can be accepted by the regulatory agency.
Requires Aircraft Limitations Report & experimental flight
test permit approval
-
8/7/2019 111910_MEC_8910A_LECTURE_6
23/59
MEC8910 2010-11 23
DEVELOPMENT TESTING
This testing phase is to explore the targetflight envelope, identify problem areas &safety margins. It can also include
certification testing dry runs.
Problem areas are assessed and resolvedthough aircraft configuration changes,
engine and/or transmission performanceincrease or aircraft limitations acceptance.
May require re-testing
-
8/7/2019 111910_MEC_8910A_LECTURE_6
24/59
MEC8910 2010-11 24
DEVELOPMENT TESTING
New Rotor
Ground resonance / Aeromechnical /Torsional Stability
Loads Performance
Handling Qualities (HQs)
Engine / drive system vibrations
Ride quality (FRAHMS)
AFCS
Initial cut at gains / scheduling
Autopilot Development
Flight Director Development
Prototype to Support Development Testing:
-
8/7/2019 111910_MEC_8910A_LECTURE_6
25/59
MEC8910 2010-11 25
PROJECT EXECUTION ENGINEERING EFFORT
DESIGN PHASE
PROTOTYPES & DEVELOPMENTFLIGHT TESTING
CERTIFICATION TESTING
COST & SCHEDULE TRACKING
TRANSPORT CANADA APPROVAL
-
8/7/2019 111910_MEC_8910A_LECTURE_6
26/59
MEC8910 2010-11 26
CERTIFICATION TESTING
Certification testing, delegated or not, isconducted to show satisfactorycompliance to regulations within definedparameters.
Aircraft configuration conformity inspection
per to test plan requirements is to becompleted prior to test start.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
27/59
MEC8910 2010-11 27
CERTIFICATION TESTING When the test is not delegated, the
regulatory agency will often conduct testplan matrix spot check or perform specifictest areas then delegate the remaining ofthe tests to the DAO.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
28/59
MEC8910 2010-11 28
CERTIFICATION TESTING
For both development & certificationtesting, some tests are dependent on
specific temperature, density altitudeand/or wind conditions. It may generateoff-site testing requirements and/or delayswaiting for the right conditions.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
29/59
MEC8910 2010-11 29
CERTIFICATION TESTING(Example Flight Tests for the New 429EP)
Load Level Survey
Hot Weather
Engine Vibration
Drive Shaft Vibration
Torsional Vibration Engine Cooling
Tailboom Temperature Survey
Hot Fuel
Oil System Test
Inlet Distortion Inlet Icing
Handling Qualities
Performance
-
8/7/2019 111910_MEC_8910A_LECTURE_6
30/59
MEC8910 2010-11 30
CERTIFICATION TESTING(Example Flight Tests for the New 429EP)
Tail Rotor Flapping
Cat A Runway
Cat A Ground Helipad
Noise Survey
Autopilot Certification
Controls Proof Load
Indirect Lightning
Cold Soak
Cockpit Cooling
Cockpit Lighting EMI / EMC
Avionics System
Function & Reliability (F&R)
-
8/7/2019 111910_MEC_8910A_LECTURE_6
31/59
MEC8910 2010-11 31
PROJECT EXECUTION ENGINEERING EFFORT
DESIGN PHASE
PROTOTYPES & DEVELOPMENTFLIGHT TESTING
CERTIFICATION TESTING
COST & SCHEDULE TRACKING
TRANSPORT CANADA APPROVAL
-
8/7/2019 111910_MEC_8910A_LECTURE_6
32/59
MEC8910 2010-11 32
COST & SCHEDULE TRACKING
Rigorous cost & schedule trackingthroughout its duration is most important in
any projects, it may seriously affect designchanges decisions.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
33/59
MEC8910 2010-11 33
COST & SCHEDULE TRACKING Cost tracking by WBSE is done by comparing
the following values: Planned to date: $ 45,000
Actual to date: $ 55, 000
Budget: $ 165,000 Estimated at completion $ 185,000
Variance (-$20,000)
Your contingency is busted and some other WBSE
contingency budgets will need to absorb it. If higheractuals were due to a scope change, the budgetwould require an increase with zero value variance.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
34/59
MEC8910 2010-11 34
COST & SCHEDULE TRACKING
Schedule tracking is done using a baselineGantt chart with regular updates to reflectactuals.
A (6 days)A (9 days)
BaselineActuals, late finish,
schedule delays & nocost impact
(3 days added)
Late start
-
8/7/2019 111910_MEC_8910A_LECTURE_6
35/59
MEC8910 2010-11 35
PROJECT EXECUTION
ENGINEERING EFFORT
DESIGN PHASE
PROTOTYPES & DEVELOPMENTFLIGHT TESTING
CERTIFICATION TESTING
COST & SCHEDULE TRACKING
TRANSPORT CANADA APPROVAL
-
8/7/2019 111910_MEC_8910A_LECTURE_6
36/59
MEC8910 2010-11 36
TCAC INVOLVEMENT Regulatory Agencies involvement, not limited
but coordinated through TCAC, throughoutthe planning & the execution phase of theprogram is essential to avoid missing out
certification requirements.
It may cause delays but it certainly reducesrisks and reworks.
Communication with regulatory agency is tobe done through the OEM/DAO Airworthinessdepartment or through the company CDs.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
37/59
MEC8910 2010-11 37
TCAC INVOLVEMENT For example, a Canadian OEM has just
obtained its TC with TCAC on a new aircraftmodel. One of its first customers is US
operator which must operate its aircraft underUS registry. During the FAA TC validationprocess, FAA decides to impose specialconditions on a particular aircraft system that
necessitate major design change. OEM inturn may lose this sale and potentially a widemarket share until it incorporates the change.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
38/59
-
8/7/2019 111910_MEC_8910A_LECTURE_6
39/59
MEC8910 2010-11 39
TCAC INVOLVEMENT
CDs should maintain weekly, if not daily,contacts with their TCAC counterpart tokeep them abreast of project development
and/or to obtain a concession/concurrenceon technical issue.
Any CD & TCAC specialist verbalagreement is to be documented (contact
report), submitted to TCAC specialist forvalidation and distributed to all involved.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
40/59
MEC8910 2010-11 40
NP&SI PROCESS SUMMARY
PHASE 1: Define Requirements & Risks
PHASE 2: Develop Concept & Risk Mitigation
PHASE 3: Pre-design Definition
PHASE 4: Design & Develop
PHASE 5: Prototyping
PHASE 6: Product Validation
PHASE 7: Transition to Manuf/Service
Gate 1
Strategic
Plan Input
Deliverables Defined
and completed beforeleaving each Gate
Gate 2
Gate 3
Gate 4
Gate 5
Gate 6
Gate 7
-
8/7/2019 111910_MEC_8910A_LECTURE_6
41/59
MEC8910 2010-11 41
PRODUCTION Factors affecting the certificated aircraft
configuration and documentation onceproduction commences can include
Modifications to the design due to The prototype aircraft were not 100%
representative of final production standard
Production easement Quicker, cheaper, fewer
parts Component reliability less than expected
New requirements: customer, foreign certification
-
8/7/2019 111910_MEC_8910A_LECTURE_6
42/59
-
8/7/2019 111910_MEC_8910A_LECTURE_6
43/59
MEC8910 2010-11 43
POST-CERTIFICATION Factors affecting the certificated aircraft
configuration and documentation post-certification include
Modifications to the design due to
In-service failures
Environmental factors
Aging aircraft
Changes to the operating and crew procedures
Maintenance tasks and their periodicity Allowable deficiencies (MMEL Master Minimum
Equipment List)
-
8/7/2019 111910_MEC_8910A_LECTURE_6
44/59
-
8/7/2019 111910_MEC_8910A_LECTURE_6
45/59
MEC8910 2010-11 45
CHANGED PRODUCT RULE
Why was Changed Product Rule introduced? To make major design changes and derivatives of older
aircraft e.g. Boeing 737 comply with the same airworthinessstandards as new designs of aircraft e.g. Airbus A320.
What happened before CPR?
Before CPRWhen a design change to an existingaeronautical product was introduced the amendment level ofthe regulations was the same as the original TC.
So the Boeing 737 derivatives (737-200, -300, -400, -500,-600, -600NG, -700, -800 and 900 were all certificated tothe same amendments as applied to the original 737 aircraft,
decades before !! The new Airbus A320, a similar aircraft to the 737, had to be
certificated to the latest amendments of the regulations.
-
8/7/2019 111910_MEC_8910A_LECTURE_6
46/59
-
8/7/2019 111910_MEC_8910A_LECTURE_6
47/59
MEC8910 2010-11 47
CHANGED PRODUCT RULE
Substantial Change
Section 511.14 and 513.14 of the CARs
require that an applicant obtain a new type
certificate if the scope and nature of theproposed change in design, configuration,
power, power limitations (engine), or
weight are so extensive that a substantially
complete investigation of compliance withthe applicable standards is required.
(Source: AC 500-016)
-
8/7/2019 111910_MEC_8910A_LECTURE_6
48/59
MEC8910 2010-11 48
CHANGED PRODUCT RULE
Substantial Change
The OEM must apply for a new TypeCertificate if the change in design, power,
thrust or weight is extensive. For example: Change from a high wing to a low wing, or vice-versa
Change of empennage configuration (from cruciform toT-tail)
Overall power/thrust increase of more than 50%
Change in flight control concept, i.e. change to fly-by-wire
-
8/7/2019 111910_MEC_8910A_LECTURE_6
49/59
MEC8910 2010-11 49
CHANGED PRODUCT RULE
Significant ChangeAdditionally, subsection 511.13(3) and 513.07(3) of the CARs
define a significant change based on whether or not one or
more of the three criteria applies:
(a) the general configuration is not retained;(b) the principles of construction are not retained; and
(c) the assumptions used for certification of the product do
not remain valid. In many cases, a significant change will
involve more than one of these criteria and will, by its
very nature, be obvious and distinct from other productimprovements or production changes.
(Source: AC 500-016)
-
8/7/2019 111910_MEC_8910A_LECTURE_6
50/59
MEC8910 2010-11 50
CHANGED PRODUCT RULE
Significant Change
The OEM must use the latest amendmentlevel (unless its impractical and/or no
impact on safety !!) if the change issignificant. For example: Change in fuselage length or diameter
Change in wing sweep angle of
-
8/7/2019 111910_MEC_8910A_LECTURE_6
51/59
MEC8910 2010-11 51
CHANGED PRODUCT RULE
How do we decide if we have aSubstantial or Significant change?
Transport Canada has published an
Airworthiness Manual Advisory AC 500-016 to help us decide
-
8/7/2019 111910_MEC_8910A_LECTURE_6
52/59
MEC8910 2010-11 52
FINAL EXAMINATIONWhat we have covered ...What we have covered ...
Types of requirement
Abbreviation & definition
NP&SI Process Risk & Contingency
Functional Hazard Analysis Criticalities
System Safety Analysis Fault Tree Analysis
-
8/7/2019 111910_MEC_8910A_LECTURE_6
53/59
MEC8910 2010-11 53
TYPES OF REQUIREMENT: ABBREVIATIONS & DEFINITION
TYPE DESIGN & TYPE CERTIFICATE
SUPPLEMENTAL TYPE CERTIFICATE (STC)
FAR, CAR, EASA, JAR, OEM, AC
IPT, NP&SI PROCESS
SPECIAL CONDITION
NPRM
EXEMPTION
EQUIVALENT LEVEL OF SAFETY
TSO
ICAO DAO, CD (DER)
CERTIFICATION BASIS & GENERAL COMPLIANCE PLAN (GCP)
DOC, NPV, ROIC, IRR
-
8/7/2019 111910_MEC_8910A_LECTURE_6
54/59
MEC8910 2010-11 54
NP&SI PROCESS SUMMARY
PHASE 1: Define Requirements & Risks
PHASE 2: Develop Concept & Risk Mitigation
PHASE 3: Pre-design Definition
PHASE 4: Design & Develop
PHASE 5: Prototyping
PHASE 6: Product Validation
PHASE 7: Transition to Manuf/Service
Gate 1
Strategic
Plan Input
Deliverables Defined
and completed beforeleaving each Gate
Gate 2
Gate 3
Gate 4
Gate 5
Gate 6
Gate 7
-
8/7/2019 111910_MEC_8910A_LECTURE_6
55/59
MEC8910 2010-11 55
CERTIFICATION
Originalapproval ofan aircraft
design
Approval of amanufacturers QCsystem to produce
aircraft that replicate theapproved design
Approval of an individualaircraft that conforms to the
type design and is in acondition for safe operation
Monitoring safetyperformance of
approved product,production QCsystem & taking
corrective action toensure continued
integrity
-
8/7/2019 111910_MEC_8910A_LECTURE_6
56/59
MEC8910 2010-11 56
Functional Hazard Assessment
Source: SAE ARP 4761
-
8/7/2019 111910_MEC_8910A_LECTURE_6
57/59
-
8/7/2019 111910_MEC_8910A_LECTURE_6
58/59
MEC8910 2010-11 58
FINAL EXAMINATION
What we have covered What we have covered
Development Removal
Managing Changes
Prototype & Development Testing
Transport Canada Approval
Production
Post-Certification (Changed Product Rule)
-
8/7/2019 111910_MEC_8910A_LECTURE_6
59/59
MEC8910 2010-11 59
CLOSING REMARKS
Anyquestions?Anyquestions?