dennon.clardy
TRANSCRIPT
New Frontiers
Discovery
February 2010 0
National Aeronautics and Space Administration
Dennon Clardy, Program ManagerDiscovery & New Frontiers
Project Management Challenge2010
Improving Life-Cycle Cost Management of Spacecraft Missions
Used with Permission
New Frontiers
Discovery
Overview of Programs
1
• Uncoupled program addressing high-priority science objectives in solar system exploration• Frequent opportunities for science community to propose full investigations• Fixed-price cost cap (cradle to grave), excluding the launch vehicle• Full and open competition• Principal Investigator-led project
• Established in 1992• $425M cap per mission (FY09)• Mission opportunities every 1.5 to 2 yr• Open science competition for all solar
system objects, except for the Earth and the Sun
• Established in 2003• $625M cap per mission (FY09)• Mission opportunities every 3 to 4 yr• Addresses high-priority investigations
identified by the National Academy of Sciences
February 2010
New Frontiers
Discovery
February 2010 2
Juno
Mars Pathfinder
CONTOUR
ASPERA-3 on Mars Express
D&NF Science Mission Targets
– The Moon (Lunar Prospector, M3, GRAIL)
– Mars (Mars Pathfinder, ASPERA-3)
– Inner Planets (MESSENGER, Strofio)
– Outer Planets (New Horizons, Juno)
– Comets (CONTOUR, Stardust, Deep Impact, EPOXI, NExT)
– Asteroids (NEAR, Dawn)
– Interplanetary Space (Genesis)
– Extra-Solar System (Kepler)
Dawn
Genesis
Stardust
MESSENGER
NEARLunar Prospector
M3 on Chadrayaan-1
New Horizons
Kepler
GRAIL
New Frontiers
Discovery
Program Organization
3
Phase B, C, D, ESMD confirmation review at end of Phase B.
SMD AA makes confirmation decision.
PM becomes heavily engaged following selection.
Programmatic Authority, Responsibility, Reporting, & Accountability
Scientific Reporting & Accountability
NASA Headquarters
Program Office
Projects
Associate Administratorfor the
Science Mission Directorate
PrincipalInvestigators
MissionProgram Executive
Project Manager(Implementing Organization)
Agency PMC
NASA Center PMC orAppointed Board
D&NF Program Executives
Mission Manager
D&NFProgram Manager
MissionProgramScientist
D&NF Program
Scientist s
D&NFProgram Director
MSFC CMC
February 2010
New Frontiers
Discovery
Study Impetus: Cost and Schedule
February 2010 4
Mission Cost Growth (percent of proposed cost)
Mission Schedule Growth (launch date slip)
Legend:Historic Mission Data Included in Study
0 00
5
10
15
20
25
30
35
40
45
50
Perc
ent C
ost G
row
th
-20.0
-10.0
0.0
10.0
20.0
30.0
40.0
50.0
60.0
Perc
ent C
ost G
row
th
Legend:Historic Mission Data Included in Study
New Frontiers
Discovery
Look for and address the “boulders” that are under the control of the program and project
Study Impetus & Research Plan
“Assess the cost escapes that have occurred on recent D&NF missions. Determine how the cost escapes are making it through our processes and determine what reasonable things we can do to either prevent them or manage them better.”
Assess LCC growth at decision gates throughout the mission development process, identifying causes affecting cost increases over the missions’ life cycle
Identify factors that contribute to the occurrence of unplanned costs and significant mission cost cap overruns
Based on findings, provide specific recommendations and implementation plans to improve current processes and provide a greater level of insight to make better-informed decisions throughout the mission life-cycle
February 2010 5
New Frontiers
Discovery
Study Implementation
INADEQUATE PLANNING FOR OPERATIONS / PHASE E Project
OPTIMISTIC HARDWARE / SOFTWARE INHERITANCE and TECHNOLOGY READINESS ASSUMPTIONS Project
INEXPERIENCED PROJECT TEAM FOR PLANETARY MISSIONS Project
INSUFFICIENT MANAGEMENT OF AND INSIGHT INTO CONTRACTOR TASKS/PERFORMANCE Project
LACK OF OR INADEQUATE INTEGRATED PROJECT SCHEDULES Project
UNIQUE/SPECIAL TASKS/WORK OUTSIDE OF AREAS OF DEMONSTRATED EXPERTISE Project
ADDITION OF NEW NASA REQUIREMENTS AFTER SELECTION Project
INSTABILITY IN NASA PROGRAM BUDGETS Project
NO LESSONS LEARNED FEEDBACK/FEEDFOWARD PROCESS Program
INADEQUATE RISK MANAGEMENT PROCESS AT TRANSITION TO IMPLEMENTATION Program
INADEQUATE CONSIDERATION OF INDEPENDENT REVIEW TEAM FINDINGS AND RECOMMENDATIONS Program
INABILITY TO PROVIDE CREDIBLE COST ESTIMATES EARLY IN DEVELOPMENT Program
February 2010 6
List of Major Findings
AssociatedRecommendations
PI’s
PM’s
PE’sTMCO
Mission Mgrs
Institutions
Mission 4Gate
Analysis
Mission 1Gate
Analysis
Mission 2Gate
Analysis
Mission 3Gate
Analysis
Mission 5Gate
Analysis
Milestone Timelines LCC & Development Histories Findings Matrices
Contributors
New Frontiers
Discovery
Major Findings
CONSIDERATION OF REVIEW TEAM FINDINGS
INEFFECTIVE MANAGEMENT STRUCTURE
INTEGRATED PROJECT SCHEDULES
INSUFFICIENT PROJECT INSIGHT
PROJECT TEAM INEXPERIENCE
INADEQUATE MISSION REPLANS
INADEQUATE PLANNING FOR OPERATIONS / PHASE E
HERITAGE and TECHNOLOGY ASSUMPTIONS
FAULT PROTECTION AND AUTONOMY
February 2010 7
We did not find a “magic bullet” in any of our findings...There is no single action that ensures cost and schedule control...
New Frontiers
Discovery
Consideration of Review Team Findings
NASA commissions senior-level expert review panels, yet does not always address (carefully consider and mitigate or refute) the panel’s conclusions and recommendations
– In most instances, cost drivers had been identified as a weakness, finding, or deficiency during reviews (source selection, milestone, or internal reviews)
– There was little evidence indicating a consistent approach to considering, analyzing, or responding to the findings and recommendations
Review teams are there to help the project: project management needs to make the best use of their knowledge and expertise
– Schedule sufficient time for review and analysis of issues (findings, issues, concerns, or actions) from reviews
– Foster a project atmosphere that moves beyond “not invented here” to ensure that issues are addressed
– Ensure follow-through with risks, liens or threats, or budget adjustments
– Document the disposition of all findings in a manner that facilitates resuscitating issues as the situation changes
February 2010 8
New Frontiers
Discovery
Ineffective Management Structure
Ineffective management structure and unclear roles and responsibilities resulted in cost and schedule impacts to missions
– Primarily occurred within projects involving multiple organizations • Inconsistent project reporting and decision-making• Unclear lines of technical authority• Unconnected systems engineering across multiple organizations• Unclear responsibility for system integration
– The management structure issues directly compounded the effects of other embedded project issues (e.g., heritage and technology problems, cost control, prime contractor inexperience, etc)
An effective Project and technical management structure should be validated and continually reassessed
– Project formulation needs to ensure a clearly documented project organizational structure, with a clear delineation of responsibilities and decision making authority
– Site visits should verify that the key parties clearly understand the organizational structure and the decision process
– Reviews should include a briefing and assessment of the effectiveness of the Project organization structure
February 2010 9
New Frontiers
Discovery
Integrated Project Schedules
The lack of a comprehensive, integrated Project schedule results in uncoordinated activities, inefficiencies in resource management, and increased costs
– Missing critical milestones and major events resulting in underestimated resources, and insufficient data for tracking performance
– Missing logical relationships (interdependencies), or unidentified or incomplete critical paths, resulting in underestimated resources, schedule delays, and poor decision making
– Multiple separate, uncoordinated schedules resulting in incomplete data for tracking performance, missing logical relationships, and unidentified critical paths
Project management should ensure valid, comprehensive, Integrated Master Schedule is in place on each project that forms the basis of and facilitates EVM reporting
– Document the proposed approach to developing and maintaining an integrated schedule, including a description of roles and processes for integrating multiple schedules, if any, into a single master schedule
– Use the Integrated Baseline Review (IBR) to confirm the content of the schedule, the processes for maintenance, and its ability to support weekly, monthly, and annual reviews and planning
– Perform a detailed review of the actual integrated schedule and associated processes as part of project milestone reviews (PDR, CDR, SIR) and periodically throughout the life cycle
February 2010 10
New Frontiers
Discovery
Insufficient Project Insight
Insufficient project management and technical insight into contractor performance results in poor communications, schedule delays, and technical problems that manifest as cost over-runs
– Specifications, processes, and procedures that did not meet institutional standards due to organization “cultural” differences or insufficient flow down of requirements
– Rework, retest, and waivers to hardware and software– Hardware mishaps– Additional personnel to perform the appropriate level of insight is added to correct issues
Project management should ensure that the structure and rationale for the approach to the insight and oversight is documented and understood at all levels
– Document the oversight approach (including rationale and staffing levels) for appropriate oversight based upon implementing center, prime contractor, and subcontractor/vendor experience
– Include a clear plan for appropriate mission assurance oversight at the prime and subcontractors/vendors
– Review and independently assess the effectiveness of their planned oversight approach at major milestones
February 2010 11
New Frontiers
Discovery
Project Team Inexperience
February 2010 12
Teams with major players with limited experience in planetary mission development are a major contributor to program management issues resulting in cost over-runs
– Complex or poorly-defined management structure, roles and responsibilities, and communications
– Inadequate development schedules and implementation of performance measuring techniques
– Inadequate performance oversight and configuration management: institute to prime and prime to sub
– Inaccurate cost estimates, inadequate cost control and management of reserves
Given there may be strategic benefits to selecting “new” team members, the Project and Program should assume a greater cost risk and operate with increased insight/oversight for less experienced team members
– Assess the relevant experience for major partners and identify associated risks– Develop mitigation plans, including mentoring and active sharing of lessons learned from
more experienced partners– Identify and carry a cost threat, adjusted to reflect continuing team performance– Review and independently assess the risks and associated mitigations at major milestones
New Frontiers
Discovery
Inadequate Mission Replans
February 2010 13
The impact of significant changes to mission scope, schedule, or funding profiles were not sufficiently understood, resulting in unexpected cost increases and schedule delays
– Program- and Project-driven changes, regardless of lifecycle timeframe, often result in underestimates of the effects (i.e., duration and complexity) on the operations phase
• Replans during development tend to concentrate on Phase C/D, so impacts to operations receive limited analysis and review
• Operations is often not well-defined early enough in the project development cycle to understand the full impact of any changes
Program and Project management need to work together to ensure sufficient time to perform a detailed assessment, develop a detailed revised baseline, and complete an independent evaluation
– Carefully consider ancillary effects such as heritage assumptions (see Heritage and Technology Assumptions)
– Specifically address any operational considerations and impacts (see Inadequate Planning for Operations/Phase E )
– Document the cost and schedule impact, along with a complete description of all associated drivers
New Frontiers
Discovery
Inadequate Planning for Operations/Phase E
February 2010 14
Phase E cost increases result from poorly scoped mission operations. Even moderate yearly underestimates can present significant LCC impacts for missions with long Phase E durations
– Early focus on hardware development schedules and cost (big ticket items)– Underestimating the complexity of the operation, ignoring special requirements for a
particular mission type, or inadequate planning for sustaining engineering
Project Management should emphasize from the beginning the need for an full and accurate life cycle cost estimate
– Emphasize the importance of a detailed operations concept that identifies plans for equipment maintenance/replacement and parts obsolescence, longevity plan for retaining/replacing key personnel
– Develop a Phase E staffing estimate by primary operations functional area that can clearly be traced to and supported by the operations concept
– Review and independently assess the operations concept and staffing estimates, including revisions to the operations concept driven by project replans
– Consider the risk of significant Phase D activities deferred into Phase E and the potential impact to operations staffing
– Manage deferred Phase D work as development effort, including appropriate metrics and schedules
New Frontiers
Discovery
Heritage and Technology Assumptions
February 2010 15
Optimistic hardware/software inheritance and technology readiness assumptions cause significant cost and schedule growth in Phases C/D
– Heritage is used to justify decreased cost and risk, but can increase cost and risk – Heritage is more than just a specific piece of hardware or software, it must be considered to
include all associated aspects (available documentation, knowledgeable personnel, operational paradigm, spacecraft design, etc.)
– New or reapplied technology may be required to enable a mission
Project Management should realistically assess both the benefits and risks associated with heritage and new technology, and ensure appropriate mitigations are identified and implemented
– Clearly demonstrate the relationship between heritage/technology rankings and cost/reserve estimates
– Create a living reference for the relationship between heritage/technology rankings and cost/reserve estimates, updated throughout formulation and implementation
– Capture high risk heritage/technology assumptions project risks and tracked for mitigation actions
– Cost factors/threats should be updated after each review, particularly heritage reviews– Review and independently assess the risks and associated mitigations at major milestones– Select membership of SRB or internal review teamsto ensure members possess needed
areas of expertise
New Frontiers
Discovery
Fault Protection and Autonomy
Missions underestimate the time and effort required to design, implement, and test fault protection and autonomy (FPA) capabilities
– Developing an integrated hardware, software, and operations approach to FPA starting early in the development life cycle
– Defining appropriate autonomy requirements and the proper level of fault protection– Estimating resource requirements, including hardware (test beds)
Institutions, programs, and projects need to develop a better understanding of the cost drivers associated with FPA to improve our processes and estimating capabilities
Project management needs to ensure FPA is addressed as a separate and equal engineering discipline
– Emphasize the importance of a comprehensive FPA approach starting with the initial system concept
– Develop an FPA development resource estimate that can clearly be traced to and supported by the operations concept
– Define FPA to the same level of maturity as the hardware and software for the mission concept throughout the mission life cycle
– Derive FPA from the operations concept, and implement a systems approach encompassing hardware, software, and operations
February 2010 16
New Frontiers
Discovery
Embedding and Impact Realization Timing
February 2010 17
Insight
Inexperience
Fault Prot.
Heritage/Tech.
Mgt. Structure
Phase E
Replan
Integrated Schedule
Impact PeriodEmbedding Period
Most FindingsEmbedded pre CR
Most ImpactsOccur post CDR
Impact PeriodEmbedding Period
Ability to descope content(cost) falls sharply post CR
Cost impacts dominate Phase D
Mitigation Actions must Focus on pre CR period in Project life cycle
Phase A(Concept Studies)
Phase B(Preliminary Design)
Phase C(Detailed Design)
Phase D(Development)
Phase E(Operations & Data
Analysis)
Formulation Implementation
SRR PDR/CRR/CR CDRLaunchMRR
FRRLRR
Phase A(Concept Studies)
Phase B(Preliminary Design)
Phase C(Detailed Design)
Phase D(Development)
Phase E(Operations & Data
Analysis)
Formulation Implementation
SRR PDR/CRR/CR CDRLaunchMRR
FRRLRR
New Frontiers
Discovery
Conclusion
February 2010 18
We did not find a “magic bullet” in any of our findings...There are no surprises here...
except that we continue to have problems in these areas
The Discovery and New Frontiers Program Office Life Cycle Cost Study was performed under the direction of Paul Gilbert (MSFC), led by Bryan Barley (MSFC), and supported by Kenny Mitchell
(MSFC-retired) and Marilyn Newhouse (CSC)
So what do we do with the results?
– First, avoid the temptation to acknowledge and then put on a shelf along with most of the previous cost growth studies
– Second, while there were no surprises, that does not mean there are no actions the entire community can take to significantly improve performance against approved budgets
– D/NF Program Office is implementing a fairly disciplined approach to • Continually identify actions we can take to avoid the traps identified in the study• Avoid the “checklist” mentality and ensure that project management activities and tools directly
contribute to planning, tracking, and controlling cost and schedule
– We are also available to engage in more detailed discussions concerning the study approach, findings, and potential actions with groups inside and outside of the D/NF community
New Frontiers
Discovery
February 2010 19
Supplemental Data and Backup
Improving the Life-Cycle Cost Management of Planetary Missions
New Frontiers
Discovery
Acronyms
February 2010 20
AO Announcement of OpportunityAR Acceptance ReviewARR ATLO Readiness ReviewATLO Assembly, Test, and Launch OperationsCDR Critical design ReviewCR Confirmation ReviewCRR Confirmation Readiness Review CSR Concept Study ReportD&NF PO Discovery and New Frontiers Program OfficeDOE Department of Energy DPI Deputy Principle InvestigatorEM Engineering ModelEVM Earned Value ManagementFPP Flight Practices and ProceduresFRR Flight Readiness ReviewFTE Full-Time EquivalentFY Fiscal YearIAT Independent Assessment TeamICE Independent Cost EstimateIRT Independent Review TeamLCC Life-Cycle CostsLRR Launch Readiness ReviewLV Launch VehicleMM Mission ManagerMOA Memorandum of AgreementMRR Mission Readiness ReviewPBR Project Budget ReportPCA Program Commitment AgreementPDR Preliminary Design Review
PDS Planetary Data SystemPI Principle InvestigatorPLRA Program Level Requirements Appendix
(to the Program Plan)PM Project ManagerPO Program OfficePSD Planetary Science DivisionRTG Radioisotope Thermoelectric GeneratorRM Resource ManagerRY Real YearSMD Science Mission DirectorateSRB Standing Review BoardSRR Systems Requirements ReviewTMCO Technical, Management, Cost, and OtherWBS Work Breakdown Structure
New Frontiers
DiscoveryBackgroundGeneric Mission Development Process
February 2010 21
Decision Gates are mission milestones at which NASA makes decisions that commit funding to a project’s Life Cycle Cost (LCC): Announcement of Opportunity (AO) Selection of Proposals – start of Phase A Selection of a project for development – start of Phase B Preliminary Design Review (PDR) Confirmation Review (CR) Program Level Requirements Appendix (PLRA) Phase C/D/E design and mission-readiness reviews
AO Development AO Implementation
Step 1 Step 2
Phase A(Concept Studies)
Phase B(Preliminary Design)
Phase C(Detailed Design)
Phase D(Development)
Phase E(Operations & Data
Analysis)
Formulation Implementation
AO Release
SRR PDR/CRR/CR CDRLaunch
6 – 24 mo 4 mo 6- 8 mo 6 – 12 mo 6 – 12 mo 24 – 36 mo 12 – 60+ mo
Competitive
Science/Mission Selection led by SMD Program Implementation led by Discovery PO
MRRFRR
LRR
AO Development AO Implementation
Step 1 Step 2
Phase A(Concept Studies)
Phase B(Preliminary Design)
Phase C(Detailed Design)
Phase D(Development)
Phase E(Operations & Data
Analysis)
Formulation Implementation
AO Release
SRR PDR/CRR/CR CDRLaunch
4 mo 6- 8 mo 6 – 12 mo 6 – 12 mo 24 – 36 mo 12 – 60+ mo
Competitive
Science/Mission Selection led by SMD Program Implementation led by Discovery PO
MRRFRR
LRR
New Frontiers
DiscoveryStudy Implementation Issues Affecting Data Collection
Collection, analysis, and synthesis of data much more intensive than anticipated
– Assumptions were made when necessary to correlate across missions, but data still valid for identifying driving issues
Lack of official/formal program documentation
– Little traceability to program-level decisions or direction (e.g., official letters, documents)
– Inconsistent records of year-to-year or life-cycle phased cost commitments and obligations to projects
Understanding of common program operating principles
– Institutions (i.e., projects) not clear on definition of cost cap
February 2010 22
Difficult to obtain and capture important/key aspects in the life of a mission due to programmatic practices
New Frontiers
Discovery
August 2007 23
High Level Summary of the Findings Timing of the Embedding and Impacts
Ability to descope content (cost) falls sharply post CR
Cost impacts dominate Phase D
Phase A(Concept Studies)
Phase B(Preliminary Design)
Phase C(Detailed Design)
Phase D(Development)
Phase E(Operations & Data
Analysis)
Formulation Implementation
SRR PDR/CRR/CR CDRLaunchMRR
FRRLRR
Phase A(Concept Studies)
Phase B(Preliminary Design)
Phase C(Detailed Design)
Phase D(Development)
Phase E(Operations & Data
Analysis)
Formulation Implementation
SRR PDR/CRR/CR CDRLaunchMRR
FRRLRR
Finding 2: Insight
Finding 8: Inexperience
Finding 6: Fault Protection
Finding 1: Heritage/Technology
Finding 7: Management Structure
Finding 3: Phase E
Finding 4: Replan
Finding 5: Integrated Schedule
Impact IntervalEmbedding Interval
Most findings embedded pre-CR Most impacts occur post-CDR