h22_saitaku10e

Upload: hung-trieu

Post on 07-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/4/2019 h22_saitaku10e

    1/18

    Study on Private-Initiative Infrastructure Projects

    in Developing Countries in FY2010

    Study on the Smart Grid Project in Ho Chi Minh City,

    the Socialist Republic of Vietnam

    SUMMARY

    March 2011

    The Ministry of Economy, Trade and Industry

    Prepared by:

    Ernst & Young ShinNihon LLC

    Japan External Trade Organization (JETRO)

    Tokyo Electric Power Services Co., Ltd.

    OPMAC Corporation

  • 8/4/2019 h22_saitaku10e

    2/18

  • 8/4/2019 h22_saitaku10e

    3/18

    Government of Vietnam(GOV) has also promoted the energy efficiency in parallel and the new energy

    efficiency law including acceleration of the energy efficiency and support for the development of

    renewable energy will be established on 1st of January in 2011.

    Regarding renewable energy, wind power / biomass / geothermal / small hydropower / Solar are considered

    as the renewable energy in Vietnam and the potential reported by IE is as follows.

    Wind Power: 1,800 MWBiomass energy: more than 150 MWGeothermal energy: 340 MWSmall hydropower: 4,000 MWSolar energy: 45 KWh/m

    2

    Small hydropower has occurred damages by flood during typhoon etc, so that the additional construction

    will be difficult by objections of inhabitants. The capacity of Biomass and Geo thermal energy is not so

    large. Therefore, Wind and Solar power will be expected to cover the increasing consumption in Vietnam.

    Especially in case of Solar energy, the generation capacity is around 3,300GW under assumption of

    utilizing 1/10 land in Vietnam.

    However, the Wind and Solar power are unstable due to the influence of weather condition, so that the

    rising of end voltage and the fluctuation of frequency are occurred. This smart grid project with EnergyManagement System(EMS) can solve the problems.

    In addition, the energy efficiency such as peak-cut and reduction of distribution loss can also contribute to

    solve the shortage of power. So, it is necessary to advance the peak-cut and the reduction of distribution

    loss by this smart grid project with Demand Response(DR) / Automated Meter Reading(AMR) and

    Advanced Distribution Automation System(DAS).

    It is important to improve the reliability of distribution network as policy of power sector. This smart grid

    project using Advanced DAS can also improve the reliability of distribution network due to reduction of

    outage duration.

    2 Fundamental policy of this project

    2.1 Fundamental policy

    This project will be recommended to implement based on the following fundamental policy.

  • 8/4/2019 h22_saitaku10e

    4/18

    Application of renewable energy such as Solar Power Solution for shortage of powerApplication of EMS to control switch of Solar power and Battery Solution for connecting to

    distribution network

    Peak-cut by DR Energy saving and efficiency

    Reduction of distribution loss by DAS and AMR Energy saving and efficiencyImprovement of reliability (reduction of outage duration) by DAS High reliability for power

    supply

    2.2 Problems and the solution

    As for promoting this project, the problems on Peak-cut by DR and Cost of solar power will be considered

    and the following solutions will be proposed.

    1) Peak-cut by DR

    Peak-cut by DR are proposed as follows.

    Large customer: Unimportant loads such as Air Conditioner(A/C) are switched off by DR.Normal customer: All of loads are switched off by DR.

    Based upon customer survey, large customers may well accept the outage of unimportant load for short

    duration (example: 30 minutes) due to no outage of important load.

    Normal (Small) customers are under outage for short duration, so that the dissatisfactions in the

    customers are concerned in spite of short outage. As for the solution, the customers can switch on by

    manual operation while the outage by DR happens. However, if most of customers will switch on, the

    effect of peak-cut decrease, so that incentive is needed to advance the effect. The following incentives

    are considered as ideas.

    If manual operation will be implemented in the state of peak-cut, the tariff becomes much higher.The cooperated customers can receive the privilege such as preferential tax or tariff.The cooperated customers can receive the citation as the cooperation.

    There are the following benefits as customers of Peak-cut by DR.

    Residential customer under the planned outage for Peak-cut can not recover the outage so far butthis proposed system can recover the power by the manual operation on condition that the customer

    pays higher tariff.

    Large customer stopped all of power under the planned outage so far but the outage by thisproposed system can be limited to unnecessary load such as A/C etc. Therefore, the important load

    such as product facilities can keep the power even though the planned outage for Peak-cut will be

  • 8/4/2019 h22_saitaku10e

    5/18

    implemented.

    Regarding the peak-cut by DR, it is necessary to consider whether there are some problems for law in

    Vietnam or not. According to Ministry of Industry and Trade(MOIT), there are no problems on lawfor the peak-cut but take care to cut off frequently because the National Diet will be possible to discuss

    due to a lot of complaints of customers. Vietnam Electricity(EVN) has already cut off the customers on

    each substation, so that we think this better outage procedure for each customer will be acceptable.

    Regarding the peak-cut by DR, there are no problems on law in Vietnam but the incentive shall be

    considered in order to accelerate the energy efficiency.

    2) Renewable energy such as Solar Cell

    According to the International Forum on Wind Energy Development of Vietnam on 5/11/2009, Solar

    Energy in Vietnam is 45 kWh / m2

    , so that the conversion to kW is around 0.1 kW / m2

    . The area of

    Vietnam land is around 330,363 k m2

    and the capability of power can be calculated as follows.

    Assumption: 1/10 in land is available for installation of Solar Power.kW x 330,000 x 106 x 1/10 = 3,300 GW

    The capability of solar power is huge and the solar is effective for solution on increasing peak load.

    However, batteries shall be equipped in order to solve unstable generation problems influenced byweather condition etc, so that the cost becomes more expensive.

    In case of Japan, the following support system on law has been carried out, so that the Solar Power

    could be expanded up to 1.4GW in 2005 and will be anticipated to reach to 1428 GW in 2020.

    Government support a part of the installation cost.Power companies have purchased with higher tariff (48 yen /kWh) for the Solar Power since

    November in 2009. However, the increased expenses on power companies can add to the normal

    tariff as green cost.

    In case of Vietnam, the supporting money for renewable energy will be considered on new law of

    energy efficiency which will be set up on 1st of January in 2011. However, the supporting money is

    small and is limited, so that the solar power will not expand widely. In order to accelerate the

    installation of solar power, not only is the cost decreased, but also the additional supporting money or

    other regulation is needed.

    When a lot of renewable plants will be connected to the distribution network in EVN, problems such as

    voltage-drop / safety etc occur. The following solutions against the problems will be considered in this

  • 8/4/2019 h22_saitaku10e

    6/18

    project and will be confirmed.

    Solar cell with battery will be installed to 2 locations.

    The reversed power and battery are monitored and controlled by EMS.EMS also monitors and controls the switch for the solar.

    2.3 Advantages

    There are mainly five economical benefits as follows.

    A) Reduction of outage duration by DAS

    B) Effective construction of Substations by DAS

    C) Reduction for technical loss of MV line with improvement of load unbalance by DASNon-technical loss reduction by AMR including smart meter

    D) Solution of power shortage by Solar power

    E) Effective construction of Power Generators by DR

    before the project(a)

    after the project(b) (a)-(b)

    A) Decrease of Power Failure373 min. 77 min.

    -296min. 4.93 h

    B) Improve of maximumaverage capacity rate of the

    substation

    75% 83% 8%

    C) Decrease of loss(technical loss of MV line)(non-technical loss)

    (1.72% (2.43%)

    (1.16% 1.3%

    -0.56% -1.13%

    D) Solar Power Generation 57,200kWh/y 57,200 kWh/y

    E) Demand Control by cuttingdemand caused by air-conditioners

    255MW2 h40 days/y

    255MW2 h40 days/y

    3 Overview of this project

    3.1 Fundamental idea of Project

    The details of this project based on the fundamental policy are as follows.

    1) Smart meter will be installed to all of customers in Phu Tho Power Company, so that AMR and DR can

    be implemented.

  • 8/4/2019 h22_saitaku10e

    7/18

    2) DR can control the following load.

    Residential customer: All of loads are switched off during short duration (ex: 30 minutes).

    Large customer: Unnecessary load except product line etc can be switched off.

    3) Solar power system with battery as asset of EVN will be installed to 2 areas as pilot project and be

    connected to MV distribution feeder directly. EMS in control center can monitor and control the reverse

    current and the battery.

    4) Servers and operator consoles for Advanced DAS with EMS are installed in Dispatch Center for existing

    Supervisory Control and Data Acquisition(SCADA) and monitor / control 110kV primary substations

    and distribution network in Phu Tho Power Company. Other servers for AMR, DR and EMS etc are

    installed in Control Center of Phu Tho Power Company and are connected to the advanced DASthrough LAN and Fiber Optic communication network.

    5) Automatic Load Break Switch(ALBS) for Over Head (OH)will be applied as new equipment.

    Automatic Ring Main Unit(RMU) for Under Ground(UG) will be also installed as new facilities in

    existing room. The existing RMU of manual type will be removed to other suitable feeder as manual

    type.

    6) Fiber Optic will be applied as backbone network of communication and ZigBee will be applied for last

    one mile communication between Remote Terminal Unit(RTU) and customers for at least 10 years.

  • 8/4/2019 h22_saitaku10e

    8/18

    3.2 Configuration of Project

    The basic system configuration including all of projects is shown in the following figure.

    Control Center

    110kV/15kV

    Substation

    Distributiion feeder

    (Overhead)

    Distributiion feeder

    (Underground)

    FCB

    LBS

    TRD

    VS

    VCB Road

    Solar Power

    RTU

    Advanced DAS Server

    Smart Meter

    Switch

    WHM

    Comunication

    AMR Server

    Console

    FCB

    VSRMU

    Battery

    PCSPCS

    RTU

    Concentrator

    Concentrator

    M-RTU

    FEP

    Optical fiber

    Network

  • 8/4/2019 h22_saitaku10e

    9/18

    3.3 Project cost

    The total amount of the project is around 42 MUS$ and the detail is explained as follows.

    Scope Quantity

    Cost

    RemarksForeignMUS$

    LocalMUS$

    1. Advanced DAS /SCADA with EMSEVN HCMCControl Center

    1 system 6.5 0.7 1. Advanced DAS with SCADA is installedin existing SCADA center and canimplement energy management ofdistribution feeder.(Solar Power)

    2. AMR/DR is installed in Pho Tho PowerCompany and is connected to AdvancedDAS by data link of Fiber Optic

    2. AMR / DRPhu Tho PowerCompany

    1 system

    3. Substation facilities 4 SS 1.2 0.2 0.3 MUS$ x 4 = 1.2 MUS$

    1st

    stage: 4 substations (110kV)2

    ndstage: expand to 34 substations

    4. New RMU 25 units 1.2 0.1 45 kUS$ x 25 = 1,125 kUS$ 1.2 MUS$

    5.New OH DASequipment

    86 units 1.3 0.1 15 kUS$ x 86 = 1,290 kUS$ 1.3 MUS$

    6. Smart Meter,Single-phase,

    Three phaseConcentrator

    90,000 units

    8,000 units196 units

    17.0 1.0120US$ x 90,000 = 10.8 MUS$

    700US$ x 8,000 = 5.6MUS$3,000US$196=0.6MUS$7. Solar Power 2 units 0.3 0.1 20kW: 0.15 MUS$

    0.15 x 2 = 0.3 MUS$

    8. Fiber Optic 0 0 0 Use existing Fiber Optic

    9.Engineering Service 1 2.5 0.7 Including Training in Japan

    Sub Total - (30.0) (2.9)

    10.TAX 1 6.6 0.3 Sub Total x 20% x 10%

    11.PhysicalContingency

    1 1.5 0.1 5% x Sub Total

    12.Price escalation 1 0.9 0.3 2.4% for Foreign8.4% for Local

    Total 39.0 3.6

    Exchange rate: $1 = 19,491VND = 80.89 yen (by Tokyo Mitsubishi UFJ bank 10/29 2010)

  • 8/4/2019 h22_saitaku10e

    10/18

    3.4 Overview of preliminary economic analysis

    The economical benefits of the project are summarized as follows.

    Economic benefit Financial benefit

    1.Decrease of Power Failure 53,512 US$/y 19,563 US$/y

    2.Improve of maximum average capacityrate in the substation

    0.939mil.US$/y Total 18.78MUS$:

    20 years)

    0.939mil.US$/y Total 18.78 MUS $:

    20 years)

    3.Decrease of loss(technical loss)(non-technical loss)

    532,476 US$/y1,074,431 US$/y

    532,476 US$/y1,074,431 US$/y

    4.Solar Power Generation5,458 US$/y 5,458 US$/y

    5.Peak Demand Control by cuttingdemand caused by air-conditioners

    -711,713 US$/y6.885 MUS$/y

    -711,713 US$/y2.470 MUS$/y

    3.4.1 Financial Analysis

    The Financial Internal Rate of Return(FIRR) of the project is of 6.90%.

    FIRR Net Present Value (NPV) Discount rate=6.95%

    Base case 6.90% -0.13 MUS$

    Initial investment increases by 10% 6.53% -1.28 MUS$Operation & Maintenance(O&M) cost increases by10%

    6.78% -0.51 MUS$

    Unit price of power purchase decreases by 10% 6.51% -1.28 MUS$

    3.4.2 Economic Analysis

    The Economic Internal Rate of Return(EIRR) of the project is of 22.79%.

    EIRR NPV

    (Discount rate=10.0%)base case 22.79 % +30.35 MUS$

    Initial investment increases by 10% 20.69% +27.43 MUS$

    O&M cost increases by 10% 22.69% +30.09 MUS$

    Construction cost of a new gas turbine power plantdecreases by 10%

    20.90% +25.49 MUS$

  • 8/4/2019 h22_saitaku10e

    11/18

    3.5 Environmental and social analysis

    3.5.1Project impact on environmental and social aspects

    Based on the JETRO Guidelines for Environmental and Social Consideration as of July 2009,

    environmental and social assessment items have been examined in this study for the future scoping

    conducted in feasibility studies and Environmental Impact Assessment(EIA) conducted at the stage of

    project implementation. When examining project impact on environmental and social aspects, check

    items in the Screening Format and the Environmental Checklist (6. Power Transmission and

    Distribution Lines) of JICA Guidelines for Environmental and Social Consideration (April 2010) have

    been referred.

    The summarized results are as follows.

    1) Sensitive Areas

    None of the sensitive areas in the following table are found.

    2) Sensitive Characteristics

    The sensitive characteristics are not applied to the project.

    3) Impacts on Environment

    Impacts on environment caused by the project implementation have been analyzed, so that there are

    slight affections but no problems due to the easy countermeasures.

    3.5.2 Environmental Legal Framework and Application to the project

    The Law on Environmental Protection (No.5212005/OH11) replaced the former law stipulated in 1993

    and has been implemented since 2006. This law is the basis of EIA and of environmental protection in

    Vietnam.

    Based on the law, this project is estimated as follows.

    1) Strategic Environmental Assessment(SEA )

    SEA is not applicable to the Project.

    2) EIA

  • 8/4/2019 h22_saitaku10e

    12/18

    EIA will not be applicable to the Project.

    3) Environmental Protection Commitment(EPC)

    The Project Owners are required to elaborate the EPC when EIA is not required. They are allowed to

    start their production and business activities after registering the EPC.

    4 Implementing schedule

    The tentative implementing schedules are estimated as shown in the following figure as Japanese ODA

    loan based on experiences.

    Implementing Schedule on Japanese ODA loan

    Item 2011 2012 2013 2014 2015

    Preparation

    Basic design and EVNHCMC / JICA appraisal

    Approval by GOJ / GOV

    E/N, L/A

    Selection of consultant

    Engineering

    Service

    Detailed Design

    Tendering StageSelection of Contractor

    Construction

    Design

    Manufacturing

    Installation and test

    Commencement

  • 8/4/2019 h22_saitaku10e

    13/18

    5 Feasibility study

    5.1 Review on Availability of Finance

    Export credit is considered as one of the finance method but Japanese ODA (Yen loan) is the best solution

    in the analyzed finance method.

    5.2 Feasibility for implementing project

    The implementation of this project is feasible as follows.

    This project corresponds to Vietnam policy to solve the shortage of power and the low reliability.This project also corresponds to the needs of EVN HCMC as implementing organization.According to economical analysis, FIRR is of6.90% and EIRR is of 22.79%.

    (In case of Japanese ODA loan, there is grace periodof 10 years and the interest rate is low such as

    1.2%.)

    5.3 Necessary activities

    It is necessary to carry out the following activities in Vietnam side in order to advance this project.

    Support of Vietnam government to accelerate the application of renewable energyIncentive for customers to allow the outage for peak-cutRequest of Japanese government support for technology and finance from Vietnam government

    6 Competitive ability of Japanese Company

    6.1 DAS

    Concerning reliability of power supply, higher technology has been already existed in Japan.

    There is strong position compare with other countries.

    Distribution network technology in Japan has progressed to solve a lot of subjects since 1960.

    DAS was also same, it was kept progressing for improvement of supply reliability and efficiently operation

    of equipment.

    This DAS is applied voltage type. There is a few countries to apply this type, but this voltage type of DAS

    should be definitely better technology than the others. The advantages are;

    Judge and split for failure section can be applied without Central Processing Unit (CPU) and

  • 8/4/2019 h22_saitaku10e

    14/18

    communication lines

    System upgrade can be applied step by step, if necessary.Initial cost should be lower than current type which is introduced in Europe.

    As of now, it is still continuing to progress for technical innovation by DAS business in Japan.

    Combine advanced DAS core technology of Japan and inexpensive distribution network equipment which

    made in China can create advantage of DAS.

    6.2 AMR System

    It is proud for higher reliability of power distribution monitoring technology which was grown in Japan.

    Advanced AMR system has been already developed by Japanese companies based on existing highertechnology.

    This advanced AMR system can realize two way communications with customers such as demand response

    and control internal switch in smart meter as well as measure power consumption at the place from far

    away.

    Having proof experiment, corporate with NEDO and the state government of New Mexico, proof

    experiment has already started that how much effect and influence will be occurred by realize real time

    pricing and DR which are told difficult in Japan to test.

    This core technology can be applied in this project as well, so that Japanese company can stand strong

    position and develop lower cost compare with the other country.

    6.3 EMS

    It is proud for higher reliability of power distribution monitoring technology which was grown in Japan.

    Advanced EMS has been already developed by Japanese companies based on existing higher technology.

    This advanced EMS can corporate efficiently between many kind of power supply such as solar power and

    wind power within smart grid and storage battery. And it is possible to be realized higher supply reliability

    and distribution network operation.

    Moreover, Curb on fluctuations equipment with storage battery which is used for to prevent influence from

    sudden out put fluctuation of Photovoltaic (PV) system, has already developed by Japanese companies.

    Relating this technology, proof experiment which will be understood effect and influence on distribution

    network in Miyakojima island by install PV system, has already started by independent type of distribution

  • 8/4/2019 h22_saitaku10e

    15/18

    network in Miyakojima of The Okinawa Electric Power Company, Inc.

    This technology can be applied in this project as well, so that Japanese company can stand strong position

    and develop lower cost compare with the other country.

    6.4 Solar Power

    Temperature of HCMC is very hot, so that the panel of crystal silicon type with high efficiency can not be

    applied to HCMC even though Japanese company has excellent competence. The panel of silicon

    amorphous type is proposed in this report due to high temperature characteristics and low cost but other

    foreign manufactures can make easily. In order to get higher power in the same space, hybrid type of

    crystal silicon and silicon amorphous will be recommendable in detail design. In this case, Japanese

    company can be applied with high competence.

    As for battery, Lithium Ion battery is recommended in this report and the development has been carried out

    in many countries. Japan also has developed as Japanese government projects, so that the high capacity

    type for storage of power will be able to get high competence.

    Furthermore, Japanese company has high competence for the inverter for solar and battery due to high

    efficiency, high characteristics and familiarity to DAS.

    6.5 Integrated System

    Under becoming aggressively for activity on smart grid, government of every country and every standard

    party also aggressively involve toadvance standardization of equipments.

    In Japan, ministry of economy, trade & industry put target to standardize in international and selected 7

    Project and 26 items as important items to keep strong position of Japanese companies.

    They proposed to IEC etc. and put target to be established within three years.

    There are 7projects as shown below.

    1) Wide-Area Situational Awareness (WASA)

    2) Storage battery for distribution network

    3) Control of distribution network

    4) DR

    5) Storage battery for consumer side

    6) Electric Vehicle (EV)

    7) Advanced Metering Infrastructure (AMI)

  • 8/4/2019 h22_saitaku10e

    16/18

    There is all necessity technology in these projects as below.

    1) DAS2) DR network

    3) Wide access communication for meters

    4) Short distance communication for meters

    5) Optimized management for storage battery for distribution

    After fix international standard, Japanese companies can be stronger position for cost competitiveness.

    In case that this proposed smart grid will be applied to Vietnam, the system and communication network

    can be applied to future technology such as Home Automation (HA), battery by EVetc, so that Japanesecompany can keep the high competence as the supplier of the system and communication network.

    7 Schedule to realize this project and the objection

    7.1 Detail schedule to realize the project

    It is necessary to implement the following activities up to starting this project by Japanese ODA loan.

    Request of this project (from Vietnam to Japanese Government): the first half in 2011Implementation of Special Assistance for Project Formation (SAPROF) by JICA Grant: in 2011E/N, L/A between Vietnam and Japanese government: the first half in 2012

    After L/A, the project such as selection of consultant etc will be implemented.

    7.2 Objection and the solution

    The priority of Vietnam for the smart grid project is lower than the current investment such as power

    generation, construction of transmission line / substation and construction of distribution feeder, so that the

    investment will be limited.

    In case of EVN HCMC, the income is around 800 MUS$ in 2009. The investment of this project is around

    40 MUS$ which is not so large as Japan but the project costmeans around 5% of the incomeas EVN

    HCMC, so that long term to realize this project will be needed due to other high priority projects. This is

    normal case for new project because client does not feel the convenience and necessity due to no

    experience.

    In order to overcome this blockade, the support of Japanese government such as Demonstration test project

  • 8/4/2019 h22_saitaku10e

    17/18

    supported by NEDO is needed to apply for the model area as pilot project.

    After the pilot project, EVN can understand the necessity and feel the benefits, so that the system using

    Japanese excellent technology can be expanded to other areas of EVN HCMC and other cities. Moreover,this system will be expected to expandto other Asian countries and become de-facto standard.

    Korea has already applied DAS project in Hai Phong as Grant and AMR project in Hanoi as also Grant. As

    for Solar system, Energy Assistance France and Schneider have applied the Build, Operate and Transfer

    (BOT) pilot project to Quang Binh province in central Vietnam. Competition between foreign countries and

    Japan are very hard but these competitive countries proposed single function as one of smart grid system.

    Japan can propose all of functions in smart grid project based on a lot of experience and excellent

    technology, so that the effect for energy efficiency in Vietnam becomes much better.

    In order to keep the highest position in smart grid system, it is important to obtain the initiative with high

    speed. Therefore, Japanese support (ex: Demonstration test project supported by NEDO) shall be quickly

    applied for Vietnam as pilot project.

  • 8/4/2019 h22_saitaku10e

    18/18

    8 Map of project area in survey country

    Project area: Phu Tho Power Company (District10 and 11) of EVN HCMC

    Scale: 1:42,000

    Dist10 and11,Project areain HCM city